If six girls can finish sweeping the floor of a hall in 45mins,how long will the same work take ten girls to do

Respuesta :

cmckee660
cmckee660 cmckee660
  • 02-05-2021

Answer:

15 minutes i think

Step-by-step explanation:

45÷6=7.5

meaning 7.5 minutes per girl

so 4 girls would be 30 minutes of work

so 45-30=15

Answer Link

Otras preguntas

five ninths times the difference of f and 32
explain the function of ribosomes and why cells need them
30-[(9x2)-(3x4)] numerical expression ;)
Diastole is: the technical name for a heart attack a form of hypertension when the ventricles relax and fill with blood the contraction of the ventricles
What is another word for cytosol
Which of the following is common for someone in stage two of HIV? A. abdominal pain and chronic pelvic pain B. diarrhea, fever, and fungal infections C. flu sym
Which of the following is common for someone in stage two of HIV? A. abdominal pain and chronic pelvic pain B. diarrhea, fever, and fungal infections C. flu sym
Earth's greenhouse effect is most directly related to the _____ cycle. a. argon b. carbon c. oxygen d. nitrogen
On Monday, David’s bank balance was $97. On Tuesday, his bank balance had changed by $56. Which amount could be the correct amount in David’s bank balance on T
M.s. alonso ordered 4,000 markers for her store. Only 1/10 of them arrived. How many markers did she receive?