In general, the production manager is responsible for the materials price variance. True or false?.

Respuesta :

PallasAthena23
PallasAthena23 PallasAthena23
  • 01-08-2022
False

In general, materials price variance is the responsibility of the purchasing manager, not the production manager.
Answer Link

Otras preguntas

4x?=298 show your work
Patricia owned so many posters that she decided to sell 77 of them to her friends.after selling the posters she still had 186 left. Write and solve an equation
Computer's hardware to perform a task is called a program, or software program. The two main types of software are system software and application software.
in what way has the spread of coal-powered factories been characteristic of the modern era
what did Abraham Lincoln learn as a result of the first battle of bull run? a) the south was unprepared for war and did not have enough troops b) the north did
The Davis Family pays $200,000 for any Wells. They make a down payment that is one tenth of the price of the house. How much is the down payment?
The Han emperor Wudi invented a bureaucratic system to help the Han run the empire what was it based upon A legalism B Confucianism C daoism D mandate of heaven
A little help plz. thx
What did madame schachter see in her vision
all summer in a day figurative language