In a project network, the critical path is the sequence of activities which has the:________.

Respuesta :

66hello60
66hello60 66hello60
  • 03-08-2022

Answer:

The correct answer is the longest time

Answer Link

Otras preguntas

Does the digestive system
look at the painting what elements does the artist use to illustrate a sense of Tranquility? check all that apply1.the use of bright shining colors 2. the use
A baseball hat is on sale for 15% off, which is $2.70. How much does the baseball hat cost at full price.
Please help 100 points if correct answer! How can you determine if an exponential equation represents exponential decay A. The initial value is negative B. T
What series of steps would result in the correct solution to the question -8(0.5y-3)=3
If f(x)=5x^3 and g(x)=x+1, find (f•g)(x)
Simplify the expression −5t+3−t−4+8t
Consider the reaction pathway graph below. Which method would provide evidence to support the inference that this is an exothermic reaction? add A and C add E a
how to resolve this problem?​
please help could not finger out​